Report_Id:   244702   Est NO  0002

Date:09/16/2024

COMMONWEALTH OF KENTUCKY

TRANSPORTATION CABINET


Contract ID 244702 Estimate Number 0002 Estimate Type PROGRESS
District Office LOUISVILLE (05340)  Martin, Bryant J.

Contractor THE TRUESDELL CORPORATION ADDR SN 0 VC Code KY0036504
1310 W 23RD STREET
TEMPE , AZ , 85282
Pay Period 08/23/2024  TO  09/05/2024
Date Approved 09/15/2024
Primary Proj Number 0505609072401
Project No. HSIP 9010(601), HSIP 9010(586), HSIP 9010(595), HSIP 9010(596), HSIP 9010(589), HSIP 9010(590), HSIP 9010(591), HSIP 9010(602)
Primary County JEFFERSON
Name of Road VARIOUS ROUTES IN DISTRICT 5
Description HFST ON SOUTHSIDE DRIVE (KY 907)
     
     
Date Let 04/25/2024 Formal Acceptance
Date Awarded 05/07/2024 Date Work Began 07/26/2024
Date Contract Executed 05/07/2024 Open To Traffic
Date NTP Issued 06/20/2024 Actual Completion Date

Current Contract Amount

$483,483.00

Total to Date

Prev to Date

This Estimate

Original Amount

$483,483.00

Total Earnings

$414,849.32

$334,041.00

$80,808.32

Percent Complete

85.80

Stockpiled Materials

$0.00

$0.00

$0.00

Funds Available

$68,633.68

Gross Earnings

$414,849.32

$334,041.00

$80,808.32

Total Change Orders

$0.00

Other Adjustments

$0.00

$0.00

$0.00

TOTAL

$414,849.32

$334,041.00

$80,808.32

Contract Id 244702

Change Order Summary

County JEFFERSON
Estimate Nbr 0002 Project Number HSIP 9010(601), HSIP 9010(586), HSIP 9010(595), HSIP 9010(596), HSIP 9010(589), HSIP 9010(590), HSIP 9010(591), HSIP 9010(602)
Contractor THE TRUESDELL CORPORATION Period 08/23/2024  TO  09/05/2024
 
 
CHANGE ORDERS HISTORY  
CHANGE ORDER NBR DESCRIPTION STATUS APPROVAL DATE TOTAL CO AMOUNT CONTRACT TIME ADJUSTED
 
 
 
 

CONTRACT ADJUSTMENTS HISTORY

Contract Adjustments

 

 

Adjustment Description

Est No

Adjustment Amount

Line Item Adjustments History
PROJECT ITEM NBR DESCRPITION TYPE EST NO

ADJ QUANTITY

UNIT PRICE

ADJUSTED AMOUNT

Contract Id 244702

COMMONWEALTH OF KENTUCKY

County JEFFERSON
Contract Type HFRS   HIGH FRICTION SURFACE

TRANSPORTATION CABINET

Primary Project Number 0505609072401
Estimate Nbr 0002 Period 08/23/2024  TO  09/05/2024
Contractor THE TRUESDELL CORPORATION
 
Project 0505600602401 Fed/State Project Number HSIP 9010(601) Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0155 TEMPORARY SIGNS 02562 SQFT 200.00 200.000 0.000 0.000 1.00 0.00
0160 MAINTAIN & CONTROL TRAFFIC 02650 LS 1.00 1.000 1.000 1.000 14,000.00 14,000.00
0165 PORTABLE CHANGEABLE MESSAGE SIGN 02671 EACH 2.00 2.000 0.000 0.000 200.00 0.00
0170 ARROW PANEL 02775 EACH 2.00 2.000 2.000 2.000 150.00 300.00
0175 PAVE MARKING-THERMO STOP BAR-24IN 06568 LF 48.00 48.000 0.000 0.000 48.00 0.00
0180 PAVE MARK TEMP PAINT STOP BAR 20099ES842 LF 48.00 48.000 0.000 0.000 22.00 0.00
0185 HIGH FRICTION SURFACE TREATMENT 23229EC SQYD 1,338.00 1,338.000 1,334.000 1,334.000 32.00 42,688.00
0190 PAVEMENT MARKING REMOVAL 40045 SQFT 96.00 96.000 96.000 96.000 19.00 1,824.00
Project 0505600602401 Fed/State Project Number HSIP 9010(601) Category 0002 DEMOBILIZATION
0195 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 6,805.62 0.00

SUBTOT

$0.00

$58,812.00

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00

 

 

 

Project 0505600642401 Fed/State Project Number HSIP 9010(586) Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0225 BARRICADE-TYPE III 02014 EACH 2.00 2.000 2.000 0.000 2.000 160.00 320.00 320.00
0230 TEMPORARY SIGNS 02562 SQFT 200.00 200.000 0.000 0.000 1.00 0.00
0235 MAINTAIN & CONTROL TRAFFIC 02650 LS 1.00 1.000 1.000 0.000 1.000 14,000.00 14,000.00 14,000.00
0240 PORTABLE CHANGEABLE MESSAGE SIGN 02671 EACH 3.00 3.000 2.000 0.000 2.000 200.00 400.00 400.00
0245 ARROW PANEL 02775 EACH 2.00 2.000 0.000 0.000 150.00 0.00
0250 HIGH FRICTION SURFACE TREATMENT 23229EC SQYD 907.00 907.000 907.000 0.000 907.000 32.00 29,024.00 29,024.00
Project 0505600642401 Fed/State Project Number HSIP 9010(586) Category 0002 DEMOBILIZATION
0255 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 6,805.57 0.00

SUBTOT

$43,744.00

$102,556.00

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00

 

 

 

Project 0505608642401 Fed/State Project Number HSIP 9010(595) Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0260 TEMPORARY SIGNS 02562 SQFT 200.00 200.000 0.000 0.000 1.00 0.00
0265 MAINTAIN & CONTROL TRAFFIC 02650 LS 1.00 1.000 1.000 1.000 14,000.00 14,000.00
0270 PORTABLE CHANGEABLE MESSAGE SIGN 02671 EACH 2.00 2.000 0.000 0.000 200.00 0.00
0275 ARROW PANEL 02775 EACH 2.00 2.000 0.000 0.000 150.00 0.00
0280 PAVE MARKING-THERMO STOP BAR-24IN 06568 LF 22.00 22.000 0.000 0.000 48.00 0.00
0285 PAVEMENT MARKING REMOVAL 06598 SQFT 44.00 44.000 44.000 44.000 24.00 1,056.00
0290 PAVE MARK TEMP PAINT STOP BAR 20099ES842 LF 22.00 22.000 0.000 0.000 22.00 0.00
0295 HIGH FRICTION SURFACE TREATMENT 23229EC SQYD 611.00 611.000 612.000 612.000 32.00 19,584.00
Project 0505608642401 Fed/State Project Number HSIP 9010(595) Category 0002 DEMOBILIZATION
0300 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 6,805.51 0.00

SUBTOT

$0.00

$137,196.00

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00

 

 

 

Project 0505609072401 Fed/State Project Number HSIP 9010(596) Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0200 TEMPORARY SIGNS 02562 SQFT 200.00 200.000 0.000 0.000 1.00 0.00
0205 MAINTAIN & CONTROL TRAFFIC 02650 LS 1.00 1.000 1.000 1.000 14,000.00 14,000.00
0210 PORTABLE CHANGEABLE MESSAGE SIGN 02671 EACH 2.00 2.000 0.000 0.000 200.00 0.00
0215 HIGH FRICTION SURFACE TREATMENT 23229EC SQYD 2,647.00 2,647.000 2,650.000 2,650.000 32.00 84,800.00
Project 0505609072401 Fed/State Project Number HSIP 9010(596) Category 0002 DEMOBILIZATION
0220 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 6,805.46 0.00

SUBTOT

$0.00

$235,996.00

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00

 

 

 

Project 0505619312401 Fed/State Project Number HSIP 9010(589) Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0050 TEMPORARY SIGNS 02562 SQFT 200.00 200.000 0.000 0.000 1.00 0.00
0055 MAINTAIN & CONTROL TRAFFIC 02650 LS 1.00 1.000 1.000 1.000 9,000.00 9,000.00
0060 PORTABLE CHANGEABLE MESSAGE SIGN 02671 EACH 2.00 2.000 2.000 2.000 200.00 400.00
0065 ARROW PANEL 02775 EACH 2.00 2.000 2.000 2.000 150.00 300.00
0070 HIGH FRICTION SURFACE TREATMENT 23229EC SQYD 556.00 556.000 556.000 556.000 32.00 17,792.00
Project 0505619312401 Fed/State Project Number HSIP 9010(589) Category 0002 DEMOBILIZATION
0075 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 6,805.46 0.00

SUBTOT

$0.00

$263,488.00

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00

 

 

 

Project 0505619312402 Fed/State Project Number HSIP 9010(590) Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0080 TEMPORARY SIGNS 02562 SQFT 200.00 200.000 0.000 0.000 1.00 0.00
0085 MAINTAIN & CONTROL TRAFFIC 02650 LS 1.00 1.000 1.000 1.000 9,000.00 9,000.00
0090 PORTABLE CHANGEABLE MESSAGE SIGN 02671 EACH 2.00 2.000 2.000 2.000 200.00 400.00
0095 ARROW PANEL 02775 EACH 2.00 2.000 2.000 2.000 150.00 300.00
0100 PAVE MARKING-THERMO STOP BAR-24IN 06568 LF 48.00 48.000 0.000 0.000 48.00 0.00
0105 PAVE MARKING-THERMO CURV ARROW 06574 EACH 4.00 4.000 0.000 0.000 96.00 0.00
0110 PAVE MARK TEMP PAINT STOP BAR 20099ES842 LF 48.00 48.000 0.000 0.000 22.00 0.00
0115 HIGH FRICTION SURFACE TREATMENT 23229EC SQYD 600.00 600.000 600.000 600.000 32.00 19,200.00
0120 PAVEMENT MARKING REMOVAL 40045 SQFT 143.00 143.000 143.000 143.000 19.00 2,717.00
Project 0505619312402 Fed/State Project Number HSIP 9010(590) Category 0002 DEMOBILIZATION
0125 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 6,805.46 0.00

SUBTOT

$0.00

$295,105.00

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00

 

 

 

Project 0505619312403 Fed/State Project Number HSIP 9010(591) Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0130 TEMPORARY SIGNS 02562 SQFT 150.00 150.000 0.000 0.000 1.00 0.00
0135 MAINTAIN & CONTROL TRAFFIC 02650 LS 1.00 1.000 1.000 1.000 17,000.00 17,000.00
0140 PORTABLE CHANGEABLE MESSAGE SIGN 02671 EACH 2.00 2.000 2.000 2.000 200.00 400.00
0145 HIGH FRICTION SURFACE TREATMENT 23229EC SQYD 2,040.00 2,040.000 2,040.000 2,040.000 32.00 65,280.00
Project 0505619312403 Fed/State Project Number HSIP 9010(591) Category 0002 DEMOBILIZATION
0150 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 6,805.46 0.00

SUBTOT

$0.00

$377,785.00

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00

 

 

 

Project 0509300422401 Fed/State Project Number HSIP 9010(602) Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0005 TEMPORARY SIGNS 02562 SQFT 200.00 200.000 0.000 0.000 1.00 0.00
0010 MAINTAIN & CONTROL TRAFFIC 02650 LS 1.00 1.000 1.000 0.000 1.000 9,000.00 9,000.00 9,000.00
0015 PORTABLE CHANGEABLE MESSAGE SIGN 02671 EACH 2.00 2.000 2.000 0.000 2.000 200.00 400.00 400.00
0020 ARROW PANEL 02775 EACH 2.00 2.000 0.000 0.000 150.00 0.00
0025 PAVE MARKING-THERMO STOP BAR-24IN 06568 LF 24.00 24.000 0.000 0.000 48.00 0.00
0030 PAVEMENT MARKING REMOVAL 06598 SQFT 48.00 48.000 48.000 0.000 48.000 24.00 1,152.00 1,152.00
0035 PAVE MARK TEMP PAINT STOP BAR 20099ES842 LF 24.00 24.000 0.000 0.000 22.00 0.00
0040 HIGH FRICTION SURFACE TREATMENT 23229EC SQYD 829.00 829.000 828.510 0.000 828.510 32.00 26,512.32 26,512.32
Project 0509300422401 Fed/State Project Number HSIP 9010(602) Category 0002 DEMOBILIZATION
0045 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 6,805.46 0.00

SUBTOT

$37,064.32

$414,849.32

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00